Byass delay may affect plans to relieve traffic congestion

Updated: 2015-09-18 09:03

By Kahon Chan in Hong Kong(HK Edition)

  Print Mail Large Medium  Small 分享按鈕 0

A half-year delay of a bypass highway to divert traffic away from the heart of Hong Kong Island will likely hold up three initiatives which could make traveling quicker. These include the city's fourth cross-harbor railway line and the long-delayed road charging scheme.

Reclamation for the Central-Wan Chai Bypass has been halted for about six months since last December. This is after contractors discovered a "large metal object" which appeared to be part of a shipwreck. Historians believe it could be the HMS Tamar which was scuttled before the Japanese occupation.

The delay has since held up completion of tunnel works until mid-2017. The Highways Department on Sept 15 confirmed contractors will not finish paving the road and installing systems before the end of 2017. This means the new bypass will miss the original commissioning date of the end of 2017. A new date has not yet been decided.

The shipwreck might only be part of the reason - according to documents provided by the Transport and Housing Bureau to the Legislative Council in March. Contractors working on the bypass had already informed builders of the Shatin to Central Link last December that handing over key sites could be delayed by six months.

The harbor-crossing commuter railway will allow commuters from Sha Tin to arrive in Admiralty via a single ride. The line will also expand the reach of the MTR to Kowloon City and To Kwa Wan. These are dense neighborhoods in Kowloon which still depend on buses for mass transit.

A spokesperson for the MTR Corporation, which will operate the rail link, told China Daily that they were not able to fully assess the impact until departments provided further details.

Former rail boss and lawmaker heading the panel on transport, Michael Tien Puk-sun, said he was worried the new rail link would miss the 2021 deadline owing to these delays.

The underwater rail between Hung Hom and Wan Chai will go under the underground highway; but the bypass has been the main thing delaying the rail project's progress. A court challenge of the bypass shifted the beginning of service from 2019 to 2020. A delay of the work-site transfer has further held up the rail launch until 2021.

Hung Wing-tat, a transport engineering expert at the Hong Kong Polytechnic University, said contractors might not be able to start working immediately after transfer of the site. Indeed, site surveying and preparations could result in last-minute design changes and add further delays to the timeline.

Tien said rail passengers might also be frustrated when new rail lines feed extra commuters into existing, overloading transit bottlenecks such as Kowloon Tong and Tsim Sha Tsui. "They may find out in the end that they are better off sticking to buses," he said.

The Tsuen Wan Line will receive commuters from Hung Hom from late 2016 when an extension of the Kwun Tong Line opens. The Shatin to Central Link will likely put further stress on the Tsuen Wan Line by 2019. The harbor-crossing section of the Tsuen Wan Line was already running at 98 percent capacity in late 2013.

Those who plan to get off trains in Hung Hom and cross the harbor by road may find this is not so easy.

Byass delay may affect plans to relieve traffic congestion

But the government believes the island bypass is an opportunity to develop new initiatives to relieve road traffic on both sides of the harbor.

However, the government disappointed motorists in 2014 when it shelved a plan to evenly distribute road traffic across three cross-harbor tunnels. They will be re-examining options after commissioning the island bypass. This is because the new road will help divert traffic to the Western Harbour Tunnel without bringing Central to a standstill.

The bypass will begin service the same year the government resumes direct control of the Eastern Harbour Crossing.

Tien believes the government may consider taking control of the tunnel after 2017. That is if traffic plans are affected by the bypass delay.

In 2015, in response to a renewed push by the Transport Advisory Committee for electronic road pricing in the Central district, the government said the bypass was an essential alternative route for motorists in order to avoid being charged in Central.

A feasibility study released over 14 years ago estimated it could take five to six years to launch a road pricing scheme. This includes a public consultation. The government had announced a plan in May to commence public engagement within this year. A statement provided by the Transport Department did not provide any update. Moreover, it did not comment on the impact of the bypass delay.

kahon@chinadailyhk.com

(HK Edition 09/18/2015 page7)

主站蜘蛛池模板: 久久久久久亚洲精品影院 | 女同另类一区二区三区 | 女性一级全黄生活片在线播放 | 国产一区二区在线播放 | 亚洲精品国产网红在线 | 亚洲国产精品一区二区第四页 | 日日干日日操 | 亚洲欧美日韩在线线精品 | 色婷婷激情五月综合 | 久久久线视频 | 日本一级毛一级毛片短视频 | 黄色一级片子 | 国产精品天天看特色大片不卡 | 欧美日韩亚洲第一页 | 精品亚洲在线 | 中文在线观看视频 | 欧美一级高清片欧美国产欧美 | 看国产一级毛片 | 国产自自拍 | 免费特级黄毛片在线成人观看 | 欧美一级中文字幕 | 久久综合网址 | 欧美毛片一级 | eeuss影院在线观看第一页 | 日本高清一级片 | 中文字幕 亚洲 一区二区三区 | 五月婷婷久久综合 | a一级黄| 免费国产黄网站在线观看视频 | 一区二区三区欧美在线 | 欧美综合激情网 | 91精品福利在线观看 | 成年视频xxxxx免费播放软件 | 久久国产免费一区二区三区 | 五月天婷婷在线视频 | 精品国产成人系列 | 日日夜夜免费精品视频 | 国产精品你懂的在线播放 | 毛片大全免费 | www国产永久免费视频看看 | 在线毛片一区二区不卡视频 |